White River Junction Revised Schedule 3.25.08 (Draft for Review and Discusssion):

This is a revised schedule for the revitalization review project showing milestones for the next couple months.

LW = Landworks
RSG = Resource Systems Group

Week of April 21

Pathways: Submit updated Utility Inventory Map with indication of utility locations, condition, and sizes. Gaps in information shall be noted.

LW: Adjust Scope, budget and longer term time frame as per review and agreement with Town of Hartford.

Month of May

LW: Distribute two draft design and development scenarios (one modest and short-term oriented, the other more ambitious and long-term oriented) for review and comment. Designs to reflect community input and to incorporate public spaces.

RSG: Estimate parking demand and potential parking solutions based on design and development scenarios and RPC build-out analysis.

Week of June 5

LW: Present revised design and development scenarios at HDC meeting based on HDC comments (materials to be received from RSG + Pathways 1 week in advance)

Present preliminary Sign and Wayfinding Plan, to be refined with branding/marketing elements as developed subsequently

Identify streetscape improvements and short and long term scenarios (to include andy refinements/additions to street furniture elements)

RSG: Present proposed parking, vehicular circulation, bicycle circulation, and pedestrian infrastructure upgrades in support of revised design and development scenarios.

Pathways: Present recommended utility infrastructure upgrades in support of revised design and development scenarios

End of June/July

LW Team: Prepare a Capital Improvement Program with costs after the Town / board approves a design and development plan. Develop initial marketing and branding concepts Final Sign and Wyafinding Plan